Loader

Wednesday April 19, 2023

Klamath Falls News

The Bureau of Reclamation, in coordination with PacifiCorp, will increase flows at Link River Dam and below Iron Gate Dam to reduce the risk of disease for salmon in the Klamath River. From April 19 through the end of the month, flows will vary on the Link and Klamath rivers.

Releases from Upper Klamath Lake through Link River Dam will increase to 5,300 cubic feet per second the morning of April 19. The increased flows will reach Iron Gate Dam late in the day, resulting in increased flows below Iron Gate Dam from the current 1,330 cfs up to a peak of around 6,030 cfs beginning late afternoon on April 19. The peak will last for 72 hours. Flows will begin ramping down at Link River Dam the morning of April 22 and that evening at Iron Gate Dam. The rampdown will last through the end of April. The public is urged to take appropriate safety precautions while flows are increased.    

Upon completion of the surface flushing flow event, Reclamation will continue to maintain Klamath River flows in accordance with the 2020 Interim Operations Plan. This surface flushing flow is an environmental compliance requirement and was implemented in coordination with the U.S. Fish and Wildlife Service, NOAA Fisheries, Tribal Nations, and Klamath Project water contractors.

Read more >

Link copied successfully